Earned Value Management Applications
Examples of calculating variances, indices, and forecasting completion costs.
Example 1: Basic EVM Calculation (Variances and Indices)
Determining project health using SV, CV, SPI, and CPI.
A construction project has a total original baseline budget of \100,00040%35%$40,000$ has been paid out so far.
Calculate the Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI), and Cost Performance Index (CPI).
Step-by-Step Solution
0 of 4 Steps Completed1
Example 2: Forecasting Completion Costs (EAC and ETC)
Calculating the Estimate at Completion and Estimate to Complete for an underperforming project.
A \500,000$500,000$200,000$250,000$.
Assuming the current cost performance inefficiencies will continue unchanged for the remainder of the project, calculate the Estimate at Completion (EAC) and the Estimate to Complete (ETC).
Step-by-Step Solution
0 of 4 Steps Completed1
Example 3: EVM for an Over-Performing Project
Calculating variances and forecasts for a project that is ahead of schedule and under budget.
A software development project has a total budget of \120,000$60,000$75,000$65,000$ (AC).
Calculate the Cost Variance (CV), Schedule Variance (SV), and the new Estimate at Completion (EAC) assuming this positive performance rate continues.
Step-by-Step Solution
0 of 5 Steps Completed1
Example 4: To-Complete Performance Index (TCPI)
Calculating the required efficiency level needed to meet the original budget goal after poor initial performance.
A project has a BAC of \80,000$30,000$40,000$80,000$ budget.
Calculate the To-Complete Performance Index (TCPI) based on the original BAC.
Step-by-Step Solution
0 of 4 Steps Completed1
Key Takeaways
- The core indices provide a snapshot of health: SPI and CPI less than indicate the project is falling behind or burning cash too fast.
- Estimating final project costs (EAC) uses the current CPI to extrapolate future spending efficiency mathematically.
- Estimate to Complete (ETC) determines exactly how much new capital is required to finish the project from the current status date forward.
- The To-Complete Performance Index (TCPI) is a goal-seeking metric, showing management exactly how efficient the team must be to recover from past losses and hit the original budget.