Indirect Costs and Profit Applications

Examples of calculating project overhead from a schedule and determining the final bid price.

Example 1: Calculating General Conditions from a Schedule

Moving away from flat percentages for hard-dollar bids.
For a highly accurate bid, an estimator must use the preliminary project schedule to calculate time-based General Conditions (Project Overhead).
A commercial building project is scheduled to last exactly 8 months8 \text{ months}.
  • Supervision: One full-time Project Manager at a burdened salary of \12,000/\text,andoneSiteSuperintendentat, and one Site Superintendent at $9,000/\text$.
  • Facilities: The site office trailer rental (including utilities and internet) is \1,500/\text$.
  • Equipment: A tower crane is needed on-site for only 4 months4 \text{ months} at a rental cost of \8,000/\text$.
  • Fixed Fees: The municipal building permit is a one-time fixed fee costing \15,000$.
Calculate the total detailed Project Overhead (General Conditions) cost.

Step-by-Step Solution

0 of 5 Steps Completed
1

Example 2: The Final Bid Price Calculation

Applying markups sequentially to reach the final bid amount.
A general contractor calculates the following raw direct costs for a small commercial building project: Materials (\500,000),Labor(), Labor ($300,000),andEquipment(), and Equipment ($100,000$).
The contractor's standard markup policies apply 10%10\% for Project Overhead, 5%5\% for General (Home Office) Overhead. Following a risk review, they add a 5%5\% Contingency for unforeseen site conditions based on the combined direct and overhead costs. Finally, the contractor desires an 8%8\% Profit margin on the entire estimated cost.
Determine the final bid price to submit to the owner.

Step-by-Step Solution

0 of 5 Steps Completed
1

Example 3: Margin vs. Markup Calculation

Understanding the mathematical difference between desired profit margin and profit markup multiplier.
A contractor calculates the total estimated cost (Direct + Indirect + Contingency) of a project to be \800,000.Thecompanysbusinessplanrequiresaguaranteed. The company's business plan requires a guaranteed 15%$ Profit Margin on the final contract price to meet its financial goals.
Calculate the required final bid price to achieve a 15%15\% margin, and determine the equivalent Markup percentage applied to the cost.

Step-by-Step Solution

0 of 5 Steps Completed
1
Key Takeaways
  • Calculating General Conditions (Project Overhead) accurately requires aligning site support costs with the expected project schedule duration, rather than applying a flat percentage to direct costs.
  • Markups must be applied sequentially; profit is typically a margin on the total estimated cost, which includes the contingency amount.
  • Estimators must clearly distinguish between Margin (percentage of revenue) and Markup (percentage of cost). A desired margin of X%X\% always requires a markup greater than X%X\%.