Earthwork Estimates Applications

Examples and applications of earthwork calculations including swell, shrinkage, and haul costs.

Example 1: Basic Volume Calculation with Swell Factor

Determine the total bank volume to be excavated and the resulting loose volume for hauling.
A highway project requires excavating a 50 m50 \text{ m} segment to lower the road grade. Station 1+0001+000 has a cut area of 45 m245 \text{ m}^2, and Station 1+0501+050 has a cut area of 60 m260 \text{ m}^2. The geotechnical report indicates the native soil has a known swell factor of 15%15\%.
Determine the total Bank Cubic Meters (BCM) to be excavated and the resulting Loose Cubic Meters (LCM) that must be hauled away by the trucking fleet.

Step-by-Step Solution

0 of 4 Steps Completed
1

Example 2: Fill Volume Calculation with Shrinkage

Calculating the required borrow pit volume to achieve a specific compacted fill volume.
A site development project requires placing 5,000 m35,000 \text{ m}^3 of compacted engineered fill (Compacted Cubic Meters, CCM) to raise the elevation for a building pad. The borrow pit material available offsite has a shrinkage factor of 12%12\% (meaning it shrinks 12%12\% from its natural bank state when fully compacted).
Calculate the volume of bank material (BCM) that must be purchased and excavated from the borrow pit to satisfy the fill requirement.

Step-by-Step Solution

0 of 3 Steps Completed
1

Example 3: Grid Method for Site Grading

Estimating earthwork for a large, relatively flat area using the grid (borrow pit) method.
A rectangular building pad measuring 20 m×30 m20 \text{ m} \times 30 \text{ m} is divided into six 10 m×10 m10 \text{ m} \times 10 \text{ m} square grids. A surveyor determines the depth of cut required at each of the 1212 grid intersection nodes. For one specific 10 m×10 m10 \text{ m} \times 10 \text{ m} grid square, the cut depths at its four corners are 1.2 m1.2 \text{ m}, 1.5 m1.5 \text{ m}, 1.1 m1.1 \text{ m}, and 1.8 m1.8 \text{ m}.
Calculate the cut volume for this single grid cell.

Step-by-Step Solution

0 of 4 Steps Completed
1

Example 4: Calculating Simple Haul Costs

Combining loose volumes, truck capacities, and cycle times to determine hauling cost.
An excavation yields 3,000 BCM3,000 \text{ BCM} of soil with a 20%20\% swell factor. A fleet of 15 LCM15 \text{ LCM} capacity dump trucks will haul the material offsite. Each truck cycle (load, haul, dump, return) takes exactly 30 minutes30 \text{ minutes} (0.5 hours0.5 \text{ hours}). The rental rate for a truck and driver is \120 / \text$.
Calculate the total transportation cost to haul all the excavated soil.

Step-by-Step Solution

0 of 5 Steps Completed
1
Key Takeaways
  • The Average End Area method is standard for linear infrastructure like highways, combining cross-sectional areas with linear stationing distances.
  • Estimators must carefully track soil states: BCM (in ground), LCM (in transit), and CCM (placed and compacted).
  • Swell factors increase BCM to find LCM. Shrinkage factors dictate how much extra BCM must be sourced to yield a specific CCM.
  • Hauling cost estimates depend entirely on converting the total dirt volume to LCM, determining truck loads, and calculating cycle times.