Project Control and Monitoring

Introduction

Project Control and Monitoring ensures that project objectives (Scope, Time, Cost, Quality) are met by comparing actual performance against the baseline plan. Deviations are identified early to implement corrective actions. Without effective control, projects can spiral out of control. Consistent monitoring allows project managers to proactively manage resources, update schedules, and manage stakeholder expectations efficiently.

Key Concepts

S-Curve

A graphical display of cumulative costs, labor hours, or percentage complete plotted against time. The curve is typically flatter at the start and end, and steeper in the middle (peak production).

Earned Value Management (EVM)

An integrated method for measuring project performance by comparing the planned value, earned value, and actual cost. It answers the question: 'Are we getting value for our money?'

Baseline

The original approved plan (scope, schedule, cost) used as a reference point for monitoring progress.

Earned Value Parameters

Core EVM Metrics

Performance Indices

Variances and Indices

Forecasting

EVM Forecasting

Key Performance Indicators (KPIs) and Claims

Non-Financial KPIs

The Claims Process

When a contractor believes they are entitled to extra time or money due to an unforeseen event, they submit an RFI, followed by a notice of delay, and eventually a formal Claim.

Important Formulas

Variance Analysis

Variances indicate the absolute deviation from the baseline in monetary or schedule terms.

Cost Variance (CV)

Indicates if the project is under or over budget.

CV=EVACCV = EV - AC

Variables

SymbolDescriptionUnit
CVCVCost Variance (Negative = Over Budget)-
EVEVEarned Value-
ACACActual Cost-

Schedule Variance (SV)

Indicates if the project is ahead or behind schedule.

SV=EVPVSV = EV - PV

Variables

SymbolDescriptionUnit
SVSVSchedule Variance (Negative = Behind Schedule)-
EVEVEarned Value-
PVPVPlanned Value-

Performance Indices

Indices indicate the relative efficiency of the project work.

Cost Performance Index (CPI)

Measures the cost efficiency of the project.

CPI=EVACCPI = \frac{EV}{AC}

Variables

SymbolDescriptionUnit
CPICPICost Performance Index (< 1.0 = Over Budget)-
EVEVEarned Value-
ACACActual Cost-

Schedule Performance Index (SPI)

Measures the schedule efficiency of the project.

SPI=EVPVSPI = \frac{EV}{PV}

Variables

SymbolDescriptionUnit
SPISPISchedule Performance Index (< 1.0 = Behind Schedule)-
EVEVEarned Value-
PVPVPlanned Value-

Progress Measurement Methods

Determining the "Earned Value" (EV) requires accurately measuring physical progress on site. Several rules of thumb are used depending on the type of work:

Measurement Techniques

Key Takeaways
  • Introduction & Concepts: Project control requires measuring actual site performance against an established baseline schedule and budget.
  • Earned Value Parameters: Understanding the difference between what was planned (PV), what was earned (EV), and what was spent (AC) is the foundation of EVM.
  • Performance Indices: SPI and CPI are powerful metrics that immediately indicate if a project is performing above or below 1.0 (the baseline efficiency).
  • Forecasting: EVM data allows project managers to mathematically predict the final project cost (EAC) based on current performance trends.
  • Important Formulas: Variances give absolute monetary or time deviations, while indices provide a relative measure of efficiency.
  • Integrated Management: Earned Value Management (EVM) is powerful because it integrates scope, schedule, and cost into a single performance measurement framework.
  • Objective Measurement: Subjective estimates of "percent complete" (e.g., "I feel like we're 80% done") destroy the value of EVM. Progress must be measured objectively using units completed or strict milestones.
  • Early Warning System: EVM indices (CPI and SPI) act as an early warning system. By month 3 of a 12-month project, the cumulative CPI is generally a highly accurate predictor of the final cost.
  • Trend over Point-in-Time: A single negative variance might be an anomaly (e.g., paying for bulk materials early). Management should focus on the trend of the indices over several periods.
  • Action Required: Monitoring without control is just observation. If EVM forecasts an overrun (EAC > BAC), the project manager must implement corrective actions immediately (e.g., changing methods, replacing underperforming subs).